BOUGHEY DISTRIBUTION ERP IMPLEMENTATION PROJECT:Project Update April 15, 2011

Posted by Boughey Distribution SAP Implementation Project in Grocery Distribution - ERP Software.
add a comment

Friday 15th March 2011

PCR commercials are agreed and work continues on existing and new requirements. We draw closer to a cut-off point where no new requirements or changes will be considered. We have some difficulty keeping ahead of the plan with our IDOC mappings in Biztalk and seek expert advice to keep this on track.

Report and Output development is on track. Training continues and intensifies on the FI side as we ramp up for go-live. The production system begins to be commissioned.

SAP
- Go-Live July 2011 (projected July 2011)
- Testing ready  September 2010 (projected February 2011)

Biztalk
- Development continues
- Go-Live April 2011 (projected April 2011)
- Testing ready October 2010 (projected March 2011)

Optimisation
- Follow-up plan to be executed

Vehicle Tracking
- Go-Live February 2011
- Training Completed

RF
- Go-Live July 2011 (projected July 2011)
- Testing ready October 2010 (projected February 2011)
- Development Progressing as expected

Directors Outstanding tasks
Go-Live strategy
Archive Plan

Commentary
Budget
On Budget
Time
SAP On Plan
Risks
IT Resource Reliance
Go-Live strategy
Stocktake requirements
SAP team resource constraints

JB Next Steps…
SAP Quality Plan

BOUGHEY DISTRIBUTION ERP IMPLEMENTATION PROJECT:Project Update March 27, 2011

Posted by Boughey Distribution SAP Implementation Project in Grocery Distribution - ERP Software, Uncategorized.
add a comment

Sunday 27th March 2011

Our internet order progresses at the speed of BT!

The PCR commercials continue and are yet to be resolved. In addition we are still identifying changes as we test existing PCR’s. This becomes a concern and we discuss whether we should now allocate some of these changes to post go-live. Unless they effect the anticipated go-live dates we will continue to develop them.

SAP
- Go-Live July 2011 (projected July 2011)
- Testing ready September 2010 (projected February 2011)

Biztalk
- Development continues
- Go-Live April 2011 (projected April 2011)
- Testing ready October 2010 (projected March 2011)

Optimisation
- Follow-up plan to be executed

Vehicle Tracking
- Go-Live February 2011
- Training Completed

RF
- Go-Live July 2011 (projected July 2011)
- Testing ready October 2010 (projected February 2011)
- Development Progressing as expected

Directors Outstanding tasks
Go-Live strategy 
Archive Plan

Commentary
Budget
On Budget
Time                     
SAP On Plan
Risks                     
IT Resource Reliance
Go-Live strategy
Stocktake requirements
SAP team resource constraints

JB Next Steps…
SAP Quality Plan

BOUGHEY DISTRIBUTION ERP IMPLEMENTATION PROJECT:Vehicle Tracking Go-Live March 20, 2011

Posted by Boughey Distribution SAP Implementation Project in Grocery Distribution - ERP Software.
1 comment so far

Sunday 20th March 2011

The vehicle tracking project goes live despite our internet problems. We are under lead time to increase the connection speed so we dual run the existing system so that the staff may become familiar with the environment but keeping track of all changes should the system become unusable.

The PCR commercials continue and are yet to be resolved.

A detailed FI training plan shows concerns around the fact that staff are very busy with their day to day duties and not being back filled during training time. We work hard to address this as training is critical with the FI go-live just 8 or so weeks away.

 SAP
- Go-Live July 2011 (projected July 2011)
- Testing ready September 2010 (projected February 2011)

Biztalk
- Development continues
- Go-Live April 2011 (projected April 2011)
- Testing ready October 2010 (projected March 2011)

Optimisation
- Follow-up plan to be executed

Vehicle Tracking
- Go-Live February 2011
- Training Completed

RF
- Go-Live July 2011 (projected July 2011)
- Testing ready October 2010 (projected February 2011)
- Development Progressing as expected

Directors Outstanding tasks
Go-Live strategy 
Archive Plan

Commentary
Budget
On Budget
Time                     
SAP On Plan
Risks                     
IT Resource Reliance
Go-Live strategy
Stocktake requirements
SAP team resource constraints

JB Next Steps…
SAP Quality Plan

BOUGHEY DISTRIBUTION ERP IMPLEMENTATION PROJECT: Project Update February 11, 2011

Posted by Boughey Distribution SAP Implementation Project in Grocery Distribution - ERP Software.
add a comment

Friday 11th February 2011 

Negotiations around the changes list continues and we work hard to identify those that are a necessity. FI is confirmed as the first go-live in order to coincide with the year end and our go-live strategy can accommodate this approach. We have a problem with our vehicle tracking project in that our internet connection is causing problems when heavily used. BT are involved in helping us resolve this. The issue list now becomes the focus of attention post realisation and the go-live strategy is to be discussed regularly until all parties are completely comfortable. 

SAP
- Go-Live July 2011 (projected July 2011)
- Testing ready September 2010 (projected February 2011)

Biztalk
- Development continues
- Go-Live April 2011 (projected April 2011)
- Testing ready October 2010 (projected March 2011)

Optimisation
- Follow-up plan to be executed

Vehicle Tracking
- Go-Live February 2011
- Training Completed

RF
- Go-Live July 2011 (projected July 2011)
- Testing ready October 2010 (projected February 2011)
- Development Progressing as expected

Directors Outstanding tasks
Go-Live strategy 
Archive Plan

Commentary
Budget
On Budget
Time      
SAP On Plan
Risks                     
IT Resource Reliance
Go-Live strategy
Stocktake requirements
SAP team resource constraints

JB Next Steps…
SAP Quality Plan

BOUGHEY DISTRIBUTION ERP IMPLEMENTATION PROJECT: Project Update January 28, 2011

Posted by Boughey Distribution SAP Implementation Project in Grocery Distribution - ERP Software.
1 comment so far

Friday 28th January 2011

Vehicle tracking training is complete. We identify the need for small departmental restructuring necessary to accommodate the complete change in working practice. It is a big change from the paper driven manual processes that exist now. We work hard to identify the PCR list and documenting the list of system changes needed to adopt our go-live strategy. We continue to discuss the go-live “order”, ie. which warehouses/customers will go first in our phased approach. FI continues to raise discussion and with the change in go-live there is a possibility that the year end (June) would be a more ideal time.

SAP
- Go-Live July 2011 (projected July 2011)
- Testing ready September 2010 (projected February 2011)

Biztalk
- Development continues
- Go-Live April 2011 (projected April 2011)
- Testing ready October 2010 (projected March 2011)

Optimisation
- Follow-up plan to be executed

Vehicle Tracking
- Go-Live February 2011
- Training Completed

RF
- Go-Live July 2011 (projected July 2011)
- Testing ready October 2010 (projected February 2011)
- Development Progressing as expected

Directors Outstanding tasks
Go-Live strategy 
Archive Plan

Commentary
Budget                
On Budget
Time                     
SAP On Plan
Risks                     
IT Resource Reliance
Go-Live strategy
Stocktake requirements
SAP team resource constraints

JB Next Steps…
SAP Quality Plan

BOUGHEY DISTRIBUTION ERP IMPLEMENTATION PROJECT: Project Update January 21, 2011

Posted by Boughey Distribution SAP Implementation Project in Grocery Distribution - ERP Software.
add a comment

Friday 21st January 2011

After a busy week reengineering the plan we agree a way forward.
We have a new go-live date.
One of the major drivers for this is that many of our customers need extra time to prepare their systems to accommodate the changes that we now require – predominantly the RF requirement for barcodes. Also, we have a significant amount of work to complete all our required reports and with the delay in recruitment it also pushes the estimated completion time back further than our original plan. In order to facilitate expected staff holidays we push the date accordingly so that the majority of them can be taken before the go-live date. The vehicle tracking project continues and training should be complete next week.

SAP
-Go-Live July 2011 (projected July 2011)
-FI to go-live last
-Testing ready September 2010 (projected February 2011)

Biztalk
-Development continues
-Go-Live April 2011 (projected April 2011)
-Testing ready October 2010 (projected March 2011)

Optimisation
-Follow-up plan to be executed

Vehicle Tracking
-Go-Live February 2011
-Training Completed

RF
-Go-Live July 2011 (projected July 2011)
-Testing ready October 2010 (projected February 2011)
-Development Progressing as expected

Directors Outstanding tasks
Go-Live strategy
Archive Plan

Commentary
Budget
On Budget
Time
SAP On Plan
Risks
IT Resource Reliance
Go-Live strategy
Stocktake requirements
SAP team resource constraints

JB Next Steps…
SAP Quality Plan

BOUGHEY DISTRIBUTION ERP IMPLEMENTATION PROJECT: Project Update January 14, 2011

Posted by Boughey Distribution SAP Implementation Project in Grocery Distribution - ERP Software.
add a comment

Friday 14th January 2011

We have a considerable amount of outstanding development of which most is changes identified during the realisation phase. I rearrange the plan to incorporate this and it suggests the go-live date is under review. We have to realign the testing/training and QA build to reflect a sensible date in line with the end of all developments and configuration. I am working hard with the board to establish a new plan.
The vehicle tracking project continues and is affecting the SAP implementation due to internal resource requirements so we look for support in this area. Our partner also experiences unforeseen resource issues which we work together to overcome as best we can.
The internal ABAP team continue to progress the necessary reports which are reviewed individually for their priority and indeed their relevance post SAP.

 SAP
- Go-Live February 2011 – April 2011 (projected April 2011)
- FI to go-live last
- Testing ready September 2010 (projected February 2011)

Biztalk
- Development continues
- Go-Live April 2011 (projected April 2011)
- Testing ready October 2010 (projected March 2011)

Optimisation
- Follow-up plan to be executed

Vehicle Tracking
- Go-Live February 2011
- Training Completed

RF
- Go-Live April 2011 (projected April 2011)
- Testing ready October 2010 (projected February 2011)
- Development Progressing as expected

Directors Outstanding tasks
Go-Live strategy 
Archive Plan

Commentary
Budget                
On Budget
Time
SAP On Plan
Risks 
IT Resource Reliance
Go-Live strategy
Stocktake requirements
SAP team resource constraints

JB Next Steps…
SAP Quality Plan
Training/Testing Plan

BOUGHEY DISTRIBUTION ERP IMPLEMENTATION PROJECT: Project Update January 7, 2011

Posted by Boughey Distribution SAP Implementation Project in Grocery Distribution - ERP Software.
add a comment

Friday 7th January 2011

After a busy Christmas for the business the New Year refocuses attention to the project.The team have taken the opportunity to take their annual leave so we start where we left off.
Over the last couple of weeks we have identified a list of outstanding requirements which will add time to the realisation phase of the project. I am working hard to make sure this does not impact go-live, but our strategy will dictate this.We organise some more training for our new ABAP team so that they may contribute further to our report requirements. It has also become apparent that there is still a significant number of customer requirements that need modification to the SAP processes.

SAP
-Go-Live February 2011 – April 2011 (projected April 2011)
-FI to go-live last
-Testing ready September 2010 (projected January 2010)

Biztalk
-Development to continue next week
-Go-Live April 2011 (projected April 2011)
-Testing ready October 2010 (projected October 2010)

Optimisation
-Follow-up plan to be executed

Vehicle Tracking
-Go-Live January 2011
-Training Completed

RF
-Go-Live April 2011 (projected April 2011)
-Testing ready October 2010 (projected December 2010)
-Development Progressing as expected

Directors Outstanding tasks
Go-Live strategy
Archive Plan

Commentary
Budget
On Budget
Time
SAP On Plan
Risks
IT Resource Reliance
Go-Live strategy
Stocktake requirements
SAP team resource constraints

JB Next Steps…
SAP Quality Plan
Training/Testing Plan

BOUGHEY DISTRIBUTION ERP IMPLEMENTATION PROJECT: Project Update December 10, 2010

Posted by Boughey Distribution SAP Implementation Project in Grocery Distribution - ERP Software.
add a comment

Friday 10th December 2010

We have a dedicated on site resource for the next few weeks to tackle the IDOC requirements for go-live and EDI.
Some modification is required and there are also decision around XML etc that we need to discuss.

SAP
- Go-Live February 2011 – April 2011 (projected April 2011)
- FI separate go-live decision to be made
- Testing ready September 2010 (projected December 2010)

Biztalk
- Development parked
- Go-Live April 2011 (projected April 2011)
- Testing ready October 2010 (projected October 2010)

Optimisation
- Follow-up plan to be executed

Vehicle Tracking
- Go-Live January 2011
- Training Completed

RF
- Go-Live April 2011 (projected April 2011)
- Testing ready October 2010 (projected December 2010)
- Development Progressing as expected

Directors Outstanding tasks
Go-Live strategy
Archive Plan

Commentary
Budget
On Budget
Time
SAP On Plan
Risks
IT Resource Reliance
Go-Live strategy
Stocktake requirements
SAP team resource constraints

JB Next Steps…
SAP Quality Plan
Training/Testing Plan

BOUGHEY DISTRIBUTION ERP IMPLEMENTATION PROJECT: Project update December 3, 2010

Posted by Boughey Distribution SAP Implementation Project in Grocery Distribution - ERP Software.
add a comment

Friday 3rd December 2010

Our new developers get stuck into their training plan and we hope they can contribute to some requirements after Christmas.
Although our RF testing is slightly behind, the developments are on target and
should be complete in the next fortnight.

SAP
-Go-Live February 2011 – April 2011 (projected April 2011)
-FI separate go-live decision to be made
-Testing ready September 2010 (projected December 2010)

Biztalk
-Development parked
-Go-Live April 2011 (projected April 2011)
-Testing ready October 2010 (projected October 2010)

Optimisation
-Follow-up plan to be executed

Vehicle Tracking
-Go-Live January 2011
-Training Completed

RF
-Go-Live April 2011 (projected April 2011)
-Testing ready October 2010 (projected December 2010)
-Development Progressing as expected

Directors Outstanding tasks
Go-Live strategy
Archive Plan

Commentary
Budget
On Budget
Time
SAP On Plan
Risks
IT Resource Reliance
Go-Live strategy
Stocktake requirements
SAP team resource constraints

JB Next Steps…
SAP Quality Plan
Training/Testing Plan

Follow

Get every new post delivered to your Inbox.