BOUGHEY DISTRIBUTION ERP IMPLEMENTATION PROJECT:Project Update April 15, 2011

Posted by Boughey Distribution SAP Implementation Project in Grocery Distribution - ERP Software.
trackback

Friday 15th March 2011

PCR commercials are agreed and work continues on existing and new requirements. We draw closer to a cut-off point where no new requirements or changes will be considered. We have some difficulty keeping ahead of the plan with our IDOC mappings in Biztalk and seek expert advice to keep this on track.

Report and Output development is on track. Training continues and intensifies on the FI side as we ramp up for go-live. The production system begins to be commissioned.

SAP
- Go-Live July 2011 (projected July 2011)
- Testing ready  September 2010 (projected February 2011)

Biztalk
- Development continues
- Go-Live April 2011 (projected April 2011)
- Testing ready October 2010 (projected March 2011)

Optimisation
- Follow-up plan to be executed

Vehicle Tracking
- Go-Live February 2011
- Training Completed

RF
- Go-Live July 2011 (projected July 2011)
- Testing ready October 2010 (projected February 2011)
- Development Progressing as expected

Directors Outstanding tasks
Go-Live strategy
Archive Plan

Commentary
Budget
On Budget
Time
SAP On Plan
Risks
IT Resource Reliance
Go-Live strategy
Stocktake requirements
SAP team resource constraints

JB Next Steps…
SAP Quality Plan

Advertisement

Comments»

No comments yet — be the first.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Connecting to %s

Follow

Get every new post delivered to your Inbox.