Our internet order progresses at the speed of BT!
The PCR commercials continue and are yet to be resolved. In addition we are still identifying changes as we test existing PCR’s. This becomes a concern and we discuss whether we should now allocate some of these changes to post go-live. Unless they effect the anticipated go-live dates we will continue to develop them.
SAP
- Go-Live July 2011 (projected July 2011)
- Testing ready September 2010 (projected February 2011)
Biztalk
- Development continues
- Go-Live April 2011 (projected April 2011)
- Testing ready October 2010 (projected March 2011)
Optimisation
- Follow-up plan to be executed
Vehicle Tracking
- Go-Live February 2011
- Training Completed
RF
- Go-Live July 2011 (projected July 2011)
- Testing ready October 2010 (projected February 2011)
- Development Progressing as expected
Directors Outstanding tasks
Go-Live strategy
Archive Plan
Commentary
Budget
On Budget
Time
SAP On Plan
Risks
IT Resource Reliance
Go-Live strategy
Stocktake requirements
SAP team resource constraints
JB Next Steps…
SAP Quality Plan