Negotiations around the changes list continues and we work hard to identify those that are a necessity. FI is confirmed as the first go-live in order to coincide with the year end and our go-live strategy can accommodate this approach. We have a problem with our vehicle tracking project in that our internet connection is causing problems when heavily used. BT are involved in helping us resolve this. The issue list now becomes the focus of attention post realisation and the go-live strategy is to be discussed regularly until all parties are completely comfortable. 

SAP
- Go-Live July 2011 (projected July 2011)
- Testing ready September 2010 (projected February 2011)

Biztalk
- Development continues
- Go-Live April 2011 (projected April 2011)
- Testing ready October 2010 (projected March 2011)

Optimisation
- Follow-up plan to be executed

Vehicle Tracking
- Go-Live February 2011
- Training Completed

RF
- Go-Live July 2011 (projected July 2011)
- Testing ready October 2010 (projected February 2011)
- Development Progressing as expected

Directors Outstanding tasks
Go-Live strategy 
Archive Plan

Commentary
Budget
On Budget
Time      
SAP On Plan
Risks                     
IT Resource Reliance
Go-Live strategy
Stocktake requirements
SAP team resource constraints

JB Next Steps…
SAP Quality Plan

Advertisement

Comments»

No comments yet — be the first.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Connecting to %s

Follow

Get every new post delivered to your Inbox.