BOUGHEY DISTRIBUTION ERP IMPLEMENTATION PROJECT: Project Update February 11, 2011
Posted by Boughey Distribution SAP Implementation Project in Grocery Distribution - ERP Software.trackback
Friday 11th February 2011
Negotiations around the changes list continues and we work hard to identify those that are a necessity. FI is confirmed as the first go-live in order to coincide with the year end and our go-live strategy can accommodate this approach. We have a problem with our vehicle tracking project in that our internet connection is causing problems when heavily used. BT are involved in helping us resolve this. The issue list now becomes the focus of attention post realisation and the go-live strategy is to be discussed regularly until all parties are completely comfortable.
SAP
- Go-Live July 2011 (projected July 2011)
- Testing ready September 2010 (projected February 2011)
Biztalk
- Development continues
- Go-Live April 2011 (projected April 2011)
- Testing ready October 2010 (projected March 2011)
Optimisation
- Follow-up plan to be executed
Vehicle Tracking
- Go-Live February 2011
- Training Completed
RF
- Go-Live July 2011 (projected July 2011)
- Testing ready October 2010 (projected February 2011)
- Development Progressing as expected
Directors Outstanding tasks
Go-Live strategy
Archive Plan
Commentary
Budget
On Budget
Time
SAP On Plan
Risks
IT Resource Reliance
Go-Live strategy
Stocktake requirements
SAP team resource constraints
JB Next Steps…
SAP Quality Plan
Comments»