BOUGHEY DISTRIBUTION ERP IMPLEMENTATION PROJECT: Project Update January 21, 2011
Posted by Boughey Distribution SAP Implementation Project in Grocery Distribution - ERP Software.trackback
Friday 21st January 2011
After a busy week reengineering the plan we agree a way forward.
We have a new go-live date.
One of the major drivers for this is that many of our customers need extra time to prepare their systems to accommodate the changes that we now require – predominantly the RF requirement for barcodes. Also, we have a significant amount of work to complete all our required reports and with the delay in recruitment it also pushes the estimated completion time back further than our original plan. In order to facilitate expected staff holidays we push the date accordingly so that the majority of them can be taken before the go-live date. The vehicle tracking project continues and training should be complete next week.
SAP
-Go-Live July 2011 (projected July 2011)
-FI to go-live last
-Testing ready September 2010 (projected February 2011)
Biztalk
-Development continues
-Go-Live April 2011 (projected April 2011)
-Testing ready October 2010 (projected March 2011)
Optimisation
-Follow-up plan to be executed
Vehicle Tracking
-Go-Live February 2011
-Training Completed
RF
-Go-Live July 2011 (projected July 2011)
-Testing ready October 2010 (projected February 2011)
-Development Progressing as expected
Directors Outstanding tasks
Go-Live strategy
Archive Plan
Commentary
Budget
On Budget
Time
SAP On Plan
Risks
IT Resource Reliance
Go-Live strategy
Stocktake requirements
SAP team resource constraints
JB Next Steps…
SAP Quality Plan