BOUGHEY DISTRIBUTION ERP IMPLEMENTATION PROJECT: Project Update January 7, 2011
Posted by Boughey Distribution SAP Implementation Project in Grocery Distribution - ERP Software.trackback
Friday 7th January 2011
After a busy Christmas for the business the New Year refocuses attention to the project.The team have taken the opportunity to take their annual leave so we start where we left off.
Over the last couple of weeks we have identified a list of outstanding requirements which will add time to the realisation phase of the project. I am working hard to make sure this does not impact go-live, but our strategy will dictate this.We organise some more training for our new ABAP team so that they may contribute further to our report requirements. It has also become apparent that there is still a significant number of customer requirements that need modification to the SAP processes.
SAP
-Go-Live February 2011 – April 2011 (projected April 2011)
-FI to go-live last
-Testing ready September 2010 (projected January 2010)
Biztalk
-Development to continue next week
-Go-Live April 2011 (projected April 2011)
-Testing ready October 2010 (projected October 2010)
Optimisation
-Follow-up plan to be executed
Vehicle Tracking
-Go-Live January 2011
-Training Completed
RF
-Go-Live April 2011 (projected April 2011)
-Testing ready October 2010 (projected December 2010)
-Development Progressing as expected
Directors Outstanding tasks
Go-Live strategy
Archive Plan
Commentary
Budget
On Budget
Time
SAP On Plan
Risks
IT Resource Reliance
Go-Live strategy
Stocktake requirements
SAP team resource constraints
JB Next Steps…
SAP Quality Plan
Training/Testing Plan
Comments»