jump to navigation

BOUGHEY DISTRIBUTION ERP IMPLEMENTATION PROJECT: Vehicle Tracking Project Kicks Off October 29, 2010

Posted by Boughey Distribution SAP Implementation Project in Grocery Distribution - ERP Software, Uncategorized.
add a comment

Friday 29th October 2010

Training plans near completion. Initially the guys will start with the basics in order to build confidence within the staff. This will also give a few weeks breathing space in order to test the complex processes (that are ready) before they are expected to train other people. The vehicle tracking project training begins, although a specific go-live date is pending our technical requirements being agreed. Additional RF costs are submitted for review accompanied by a comprehensive ROI document! My attentions are also drawn back to our Biztalk development as this is now slipping. This is due to the increased amount of development work in the SAP project. My attentions are also drawn back to our Biztalk development as this is now slipping. This is due to the increased amount of development work in the SAP project.

SAP
- Go-Live February 2011 – April 2011 (projected April 2011)
- FI separate go-live decision to be made
- Testing ready September 2010 (projected November 2010)
- Graduate Developer Recruitment in progress
- IT Manager Recruitment in progress

Biztalk
- Development parked
- Go-Live April 2011 (projected April 2011)
- Testing ready October 2010 (projected October 2010)

Optimisation
- Development meeting parked
- Follow-up plan to be executed

Vehicle Tracking
- Go-Live Date Pending Contract
- Training Started

RF
- Go-Live April 2011 (projected April 2011)
- Testing ready October 2010 (projected December 2010)
- Development Progressing as expected

Directors Outstanding tasks
Go-Live strategy
Meeting with customers
Archive Plan
Training Plan

Commentary
Budget
On Budget – Additional RF Hardware/Development
Time
SAP On Plan
Tracking – Behind Plan
Risks
IT Resource Reliance
Go-Live strategy
Stocktake requirements
SAP team resource constraints

JB Next Steps…
SAP Quality Plan
Training/Testing Plan

BOUGHEY DISTRIBUTION ERP IMPLEMENTATION PROJECT: Training/Testing Preparations October 22, 2010

Posted by Boughey Distribution SAP Implementation Project in Grocery Distribution - ERP Software.
add a comment

Friday 22nd October 2010

The training facilities are sourced and ordered to arrive in good time for the
start of our phase. The team complete their plans and start their own
worksheet for personal SAP training.
The vehicle tracking project gets under way and training plans and dates
are confirmed for the end of the month.
I also decide to change the Managers/Key personnel meeting to weekly.
Recruitment of a developer continues to prove fruitless.
 
SAP
- Go-Live February 2011 – April 2011 (projected April 2011)
- FI separate go-live decision to be made
- Testing ready September 2010 (projected November 2010)
- Graduate Developer Recruitment in progress
- IT Manager Recruitment in progress
 
Biztalk
- Development parked
- Go-Live April 2011 (projected April 2011)
- Testing ready October 2010 (projected October 2010)
 
Optimisation
- Development meeting parked
- Follow-up plan to be executed
 
Vehicle Tracking
- Go-Live Date Pending Contract
- Technical Meeting complete – Specification to be signed
 
RF
- Go-Live April 2011 (projected April 2011)
- Testing ready October 2010 (projected December 2010)
- Development Progressing as expected
 
Directors Outstanding tasks
Go-Live strategy 
Plan to inform customers
Archive Plan
Training Plan
 
Commentary
Budget
On Budget – Additional RF Hardware/Development
Time
SAP On Plan
Tracking – Behind Plan
Risks
IT Resource Reliance
Go-Live strategy
Stocktake requirements
SAP team resource constraints
                                
 
JB Next Steps…
SAP Quality Plan
Training/Testing Plan

BOUGHEY DISTRIBUTION ERP IMPLEMENTATION PROJECT: Training/Testing Preparations October 19, 2010

Posted by Boughey Distribution SAP Implementation Project in Grocery Distribution - ERP Software, Uncategorized.
add a comment

 

Friday 15th October 2010

The team are tasked with compiling both their training and testing plans for their individual areas. As the realisation phase continues towards completion the knowledge transfer plans are started. These will be one-on-one discussions between our internal team and the consultants – sort of a start to a “train the trainer” approach.The optimisation system is now live and I task the team with a follow-up plan to facilitate working through any operational queries etc. We need to analyse the effect of the changes in our working practices. The deadline for our extra RF hardware requirements gets closer due to lead-times for installations – so this  acquires urgent status.We require some additional data from our customers in order to facilitate the extra requirements of WM.

SAP
- Go-Live February 2011 – April 2011 (projected April 2011)
- Training facilities need to be arranged
- FI separate go-live decision to be made
- Fortnightly Managers Meetings underway
- Testing ready September 2010 (projected November 2010)
- Graduate Developer Recruitment in progress
- IT Manager Recruitment in progress

Biztalk
- Development parked
- Go-Live April 2011 (projected April 2011)
- Testing ready October 2010 (projected October 2010)

Optimisation
- Development meeting parked
- Follow-up plan to be executed

Vehicle Tracking
- Go-Live Date Pending Contract
- Technical Meeting complete – Specification to be signed

RF
- Go-Live April 2011 (projected April 2011)
- Testing ready October 2010 (projected December 2010)
- Development Progressing as expected

Directors Outstanding tasks
Plan to inform customers
Archive Plan
Training Plan

Commentary
Budget
On Budget – Additional RF Hardware/Development
Time
SAP On Plan
Tracking – Behind Plan
Risks
IT Resource Reliance
Go-Live strategy
Stocktake requirements
SAP team resource constraints

JB Next Steps…
SAP Quality Plan
Training/Testing Plan

BOUGHEY DISTRIBUTION ERP IMPLEMENTATION PROJECT: SAP Baseline Review Complete October 19, 2010

Posted by Boughey Distribution SAP Implementation Project in Grocery Distribution - ERP Software.
add a comment

Friday 8th October 2010

Stage 1 of the SAP realisation project is marked by a “baseline review” in which the SAP team demonstrate the basic configured processes within our solution. I meet with key personnel in the business to introduce our thoughts on a training and testing plan. Everyone seems upbeat and the meeting is positive. We will hold these meetings once a fortnight to provide a forum for feedback and updates.

The vehicle optimisation project needs finalising as some users find it more time consuming than others to make the transition. We also find a small technical problem that is manageable but nonetheless needs resolving.

The tracking project kicks off and our supplier spends some time in the department to get a feel for the workflow. This should be a fairly straightforward project as it almost runs in isolation, but will be much more integrated with our SAP system. RF development makes good progress and to ensure we meet original deadlines extra resource is applied. For unit testing we have requirements for good test data to be created in order to fully verify the developments.

SAP
- Go-Live February 2011 – April 2011 (projected April 2011)
- Testing & Training to start first week November
- FI separate go-live decision to be made
- JB /managers meeting every fortnight
- DR Plan to be discussed
- Testing ready September 2010 (projected November 2010)
- Graduate Developer Recruitment in progress
- IT Manager Recruitment in progress

Biztalk
- Development parked
- Go-Live April 2011 (projected April 2011)
- Testing ready October 2010 (projected October 2010)

Optimisation
- Meeting with Paragon re Development Parked
- Final cutover outstanding

Vehicle Tracking
- Go-Live Date Pending Contract
- Awaiting Plan

RF
- Go-Live April 2011 (projected April 2011)
- Testing ready October 2010 (projected December 2010)
- Problems with lack of test data to be reviewed

Directors Outstanding tasks
Go-Live strategy
Plan to inform customers
Archive Plan
Training Plan

Commentary
Budget
On Budget – Additional RF Hardware/Development
Time
SAP On Plan
Tracking – Behind Plan
Risks
IT Resource Reliance
Go-Live strategy
Stocktake requirements
SAP team resource constraints

JB Next Steps…
SAP Quality Plan
Training/Testing Plan

BOUGHEY DISTRIBUTION ERP IMPLEMENTATION PROJECT Training comes into view October 1, 2010

Posted by Boughey Distribution SAP Implementation Project in Grocery Distribution - ERP Software, Uncategorized.
1 comment so far

Friday 1st October 2010

 
The Optimisation project goes live as expected – it is difficult as people get up to speed in a live environment, i.e. coupled with constant queries and other daily duties but the team work tirelessly to make it happen. The SAP training will start at the beginning of November and therefore we have a deadline for facilities to be in place. I want each person in the business to have at least 1-2 hours of SAP exposure from then on in. We champion one of our internal IT team to investigate our proposals for a go-Live strategy. We also explore the possibility of moving forward earlier with the FI module. All the pros and cons are in discussion.

SAP
- Go-Live February 2011 – April 2011 (projected April 2011)
- Testing & Training to start first week November
- Testing ready September 2010 (projected November 2010)
- Graduate Developer Recruitment in progress
- IT Manager Recruitment in progress

Biztalk
- Development parked
- Go-Live April 2011 (projected April 2011)
- Testing ready October 2010 (projected October 2010)

Optimisation
- Go-Live August 2010 (actual 27th September)
- Development meeting parked

Vehicle Tracking
- Go-Live Date Pending Contract
- Awaiting Plan
- Technical Meeting complete – Specification to be signed

RF
- Go-Live April 2011 (projected April 2011)
- Testing ready October 2010 (projected December 2010)
- Workshops complete and development started

Directors Outstanding tasks
Go-Live strategy
Plan to inform customers
Archive Plan
Training Plan

Commentary
Budget
On Budget – Additional RF Hardware/Development
Time
SAP On Plan
Tracking – Behind Plan
Risks
IT Resource Reliance
Go-Live strategy
Stocktake requirements
WM configuration on internal staff

JB Next Steps…
SAP Quality Plan
Training/Testing Plan

Follow

Get every new post delivered to your Inbox.